Calumpit Main Site Yard of the PNR Clark Phase 1
« on: October 18, 2019, 01:54:50 PM »
Administrator’s note: See also Malolos-Balagtas-Guiginto Stations


https://www.facebook.com/DOTrPH/posts/1488138957991902

Actual construction works at the Calumpit Main Site Yard of the PNR Clark Phase 1 (Manila-Bulacan)!

This facility located in Calumpit, Bulacan is a 14-hectare area that serves as the main production site for the precast segments of Contract Package 2 of the PNR Clark Phase 1. CP02 covers the construction works for three stations, namely, Balagtas, Guiginto, and Malolos.

This yard will include a batching plant for the supply of concrete to expedite precast segment production and other fabrication requirements.

Ongoing works at the yard include backfilling, which is now at 98% progress rate, piling which is targeted to be completed by mid-November, and the foundation works for the establishment of the Engineer's Office and Site Laboratory.

Furthermore, various specialized equipment such as the Tower Crane and Gantry Crane are expected to arrive soon to complement the ongoing site development work.

Transportation Secretary Arthur Tugade has ordered work to be done 24/7 to accelerate completion of the project, and has mandated the consultants to provide a daily progress report.

Once PNR Clark Phase 1 is fully operational, the 37.6-kilometer mass railway system will reduce travel time between Manila and Bulacan from one (1) hour and 30 minutes to just 35 minutes. This rail line is expected to serve 300,000 passengers daily.

====









« Last Edit: October 19, 2019, 10:43:42 PM by adroth »

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11909
    • View Profile
    • The ADROTH Project
Re: Calumpit Main Site Yard of the PNR Clark Phase 1
« Reply #1 on: October 18, 2019, 01:57:32 PM »













adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11909
    • View Profile
    • The ADROTH Project
Re: Calumpit Main Site Yard of the PNR Clark Phase 1
« Reply #2 on: January 18, 2020, 01:13:02 PM »
https://www.facebook.com/DOTrPH/posts/1588756731263457

Actual construction works at the Calumpit Main Site Yard of the ongoing PNR Clark Phase 1 (Tutuban-Malolos)!

This facility located in Calumpit, Bulacan is a 14-hectare area that serves as the main production site for the precast segments of Contract Package 2 of the PNR Clark Phase 1. CP02 covers the construction works for three stations, namely, Balagtas, Guiginto, and Malolos.

This yard will include a batching plant for the supply of concrete to expedite precast segment production and other fabrication requirements.

Once PNR Clark Phase 1 is fully operational, the 38-km elevated rail line will reduce travel time between Manila and Bulacan from one (1) hour and 30 minutes to just 35 minutes.

The rail line is expected to serve 300,000 passengers daily.

====














adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11909
    • View Profile
    • The ADROTH Project
Re: Calumpit Main Site Yard of the PNR Clark Phase 1
« Reply #3 on: January 31, 2020, 03:49:17 PM »
https://www.facebook.com/DOTrPH/posts/1599966776809119

From forms and rebars, the precast segment at the Calumpit Main Site Yard—a 14-hectare area that serves as the main production site for the precast segments of Contract Package 2 of the project—can now be seen!

With the construction works rolling out at an accelerated pace, the first segment for the project was casted last 23 January 2020, while the second casting will commence this evening, 29 January 2020.

The peak production of the segments will begin March 2020, with about 5 precast segments to be produced each day.

Approximately, 12 to 15 pieces of the precast segment will encompass the project's pier to pier viaduct.

Once PNR Clark Phase 1 is fully operational, the 38-km elevated rail line will reduce travel time between Manila and Bulacan from one (1) hour and 30 minutes to just 35 minutes. The rail line is expected to serve 300,000 passengers daily.

===









« Last Edit: January 31, 2020, 03:52:25 PM by adroth »

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11909
    • View Profile
    • The ADROTH Project
Re: Calumpit Main Site Yard of the PNR Clark Phase 1
« Reply #4 on: February 19, 2020, 09:12:49 AM »
https://www.facebook.com/DOTrPH/posts/1614219445383852

FULL BLAST construction for the PNR Clark Phase 1 (Tutuban-to-Malolos)!

Following the inspection led by DOTr Assistant Secretary for Railways Fidel Cruz, six segments have already been casted at the Calumpit Main Site Yard—a 14-hectare area that serves as the main production site for the precast segments of Contract Package 2 of the project.

PNR Clark Phase 1 is a 38-kilometer mass railway transportation that will connect Tutuban, Manila to Malolos, Bulacan. It forms part of the mega railway network, the North-South Commuter Railway (NSCR).

Approximately, 12 to 15 pieces of the precast segment will encompass the project's pier to pier viaduct.

Once PNR Clark Phase 1 is fully operational, the elevated rail line will reduce travel time between Manila and Bulacan from one (1) hour and 30 minutes to just 35 minutes. The rail line is expected to serve 300,000 passengers daily.

=====