Re: Road-right-of-way issues with Mindanao Railway
« Reply #15 on: January 15, 2020, 03:47:58 PM »
https://www.facebook.com/DOFPH/photos/a.280593182101972/1330922533735693/?type=3&theater

DID YOU KNOW THAT THE REAL PROPERTY VALUATION REFORM CAN HELP ACCELERATE INFRASTRUCTURE DEVELOPMENT?

The current multiple, outdated, and overlapping real property valuations complicate the acquisition of land and road right-of-way (ROW) for infrastructure projects.

By harmonizing the values and adopting a professional, credible, and transparent valuation system, the Real Property Valuation Reform or the Package 3 of the Comprehensive Tax Reform Program (CTRP) will help address these land and road ROW acquisition issues that have caused major delay to some of the government's vital infrastructure projects such as the Build, Build, Build program.

Package 3 proposes to:
✔️ adopt internationally accepted valuation standards
✔️ use single valuation for land transactions taxation
✔️ use schedule of market values as benchmark for ROW acquisition
✔️ strengthen the valuation arm of the DOF-attached Bureau of Local Government Finance

READ MORE: https://taxreform.dof.gov.ph/tax-reform-packages/p3-real-property-valuation/

=====



adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 14368
    • View Profile
    • The ADROTH Project
Re: Road-right-of-way issues with Mindanao Railway
« Reply #16 on: January 17, 2020, 04:58:59 AM »
It’s single-track, diesel-run railway for Tagum, Davao, Digos
By MINDANEWS -JANUARY 16, 2020 5:00 PM

https://www.mindanews.com/top-stories/2020/01/its-single-track-diesel-run-railway-for-tagum-davao-digos/

< Edited >

Eje said the selection of consultant and contractor goes through a process, and civil works can proceed after the groundbreaking.

After the selection the DOTr will bid out the project, he said.

He assured Mindanawons that the agency was doing all it can to get the project started immediately and completed before the end of the term of President Rodrigo R. Duterte in 2022.

He said the agency is working double-time to complete the acquisition of the road right of way.

At present, he said, there is “evaluation and validation” for the properties located along the railway path to make sure the right owners and not just any other claimants get compensated.

“Once the appraisers complete the validation, the processing of the payment will immediately proceed. If you will remember, during the survey, malapad yung sinusurvey namin (the area surveyed was so wide), but it does not necessarily mean yung buong yung dadaanan, kasi may adjustments kung saan matatamaan (all of it will be covered since adjustments were made),” he said.

< Edited >

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 14368
    • View Profile
    • The ADROTH Project
Re: Road-right-of-way issues with Mindanao Railway
« Reply #17 on: January 30, 2020, 03:27:14 PM »
Road-right-of-way markers in Baliok, Toril. These reportedly went up in November last year

https://www.facebook.com/groups/rpdefense/permalink/2696422620443568/






adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 14368
    • View Profile
    • The ADROTH Project
Re: Road-right-of-way issues with Mindanao Railway
« Reply #18 on: February 11, 2020, 02:32:58 PM »


adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 14368
    • View Profile
    • The ADROTH Project
Re: Road-right-of-way issues with Mindanao Railway
« Reply #20 on: March 20, 2020, 07:31:05 AM »

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 14368
    • View Profile
    • The ADROTH Project
Re: Road-right-of-way issues with Mindanao Railway
« Reply #21 on: March 20, 2020, 09:49:49 AM »
The following flowchart was shared by the DOTr during a public consultation at Deca Homes, Catalunan Grande, in February 2020



adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 14368
    • View Profile
    • The ADROTH Project
Re: Road-right-of-way issues with Mindanao Railway
« Reply #22 on: March 21, 2020, 11:41:56 AM »
From August 2018

https://www.facebook.com/barangaybagooshiro/posts/901116976762832

Pahibalo! Adunay pagahimuon nga Information Education Campaign mahitungod sa MINDANAO RAILWAY PROJECT (RILES SA TRAIN)nga muagi sa atong Barangay partikular na sa Purok 10, Purok 6, Purok 5A ug 5B (duol sa Sta. Lucia) ugma, Agosto 24, 2018 sa ala 1:00 sa hapon sa Brgy. Gym. Ginaimbitahan ang mga lumulupyo sa maong lugar aron makabalo ug makasabot sa maong proyekto ug kini usab ang panahon nga mapagawas nila ang ilang mga pangutana mahitungod niini nga proyekto nga diin anaa usab ang saktong mga personalidad nga mutubag niini.Daghang Salamat.

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 14368
    • View Profile
    • The ADROTH Project
Re: Road-right-of-way issues with Mindanao Railway
« Reply #23 on: August 05, 2020, 12:53:33 PM »
Regional Updates (07/22/20)
July 23, 2020 | 1:00 am

https://www.bworldonline.com/regional-updates-07-22-20/

< Edited >

PRE-CONSTRUCTION

Meanwhile, Project Manager Clipton J. Solamo said they are aiming to complete all the pre-construction activities by the third quarter this year. This involves right-of-way (ROW) and site acquisition, area inspections, project alignment, and meetings with officials and residents of affected communities. “We are targeting to finish the pre-construction works within the third quarter of this year,” Mr. Solamo said in a text message. The National Economic and Development Authority approved a single track, diesel-run railway system for the initial segment, but Mr. Eje said they are acquiring a 40-meter wide ROW for the entire line as a provision for a possible upgrade to a dual track electric system in the future. — Maya M. Padillo

< Edited >

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 14368
    • View Profile
    • The ADROTH Project
Re: Road-right-of-way issues with Mindanao Railway
« Reply #24 on: September 12, 2020, 03:16:48 PM »
https://www.facebook.com/MindanaoRailWatch/posts/3077623622505037

A community member shared the following sketch plan of a property in Catalunan Grande that will be affected by the Mindanao Railway Project. To protect the owner's privacy, the owner's name, the specific lot, and other identifiers were removed. Note that half of the property will be taken up by the right-of-way.



adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 14368
    • View Profile
    • The ADROTH Project
Re: Road-right-of-way issues with Mindanao Railway
« Reply #25 on: September 24, 2020, 02:42:24 AM »
I sent that message to both the Pag-IBIG official email address as well as the Mindanao Railway Project Office (MRPO). The MRPO responded first.





From the looks of it, a lot of the balls are in Pag-IBIG's court. After I forwarded them the MRPO's email, I finally got the following result