Mindanao Railways Cagayan-Iligan Corridor Line Stations IdentifiedBy CDODev Admin - September 5, 2009
http://www.cdodev.com/2009/09/05/mindanao-railways-cagayan-iligan-corridor-line-stations-identified/The proposed Cagayan-Iligan Corridor Line of the Mindanao Railways project will have main terminals at Linamon and Jasaan. According to the proposal, Express Stations will be put up at Iligan Port, Laguindingan Airport, and Agora Terminal in Cagayan de Oro City. Intermediate stations will be constructed in each municipality along the corridor.
In previous gatherings, Cagayan de Oro City Mayor Constantino Jaraula said the proposed project will construct elevated railways in both Iligan and Cagayan de Oro because of space limitations. In Cagayan de Oro City, from Opol, it will pass beside Westbound (Bulua) Terminal acorss Ayala Property then proceed towards and along the 5th bridge then another elevated railway up to Agora Terminal similar to the MRT/LRT system in Metro Manila.
< Edited >
====
Gov't to prioritize Mindanao RailwayBy CDODev Admin - November 23, 2010 296 0
http://www.cdodev.com/2010/11/23/govt-to-prioritize-mindanao-railway/The government is exploring the possibility of prioritizing the development of the proposed Mindanao Railway, a proposal which was originally hatched during the Estrada administration and was pushed by then ARMM chairman Nur Misuari.
“Explore the possibility of prioritizing the Mindanao Railway,” stated an aide memoire of the National Economic and Development Authority following the recent consultation on the chapter on infrastructure under the 2010-2016 Medium-Term Philippine Development Plan.
Most recent project estimates have placed the total project cost at P66.5-billion, approximately $1.33-billion.
It is envisioned to be implanted in four phases: initially from Laguindingan to Cagayan de Oro City; second from Laguindingan to Iligan City ; third from Cagayan de Oro to Phividec area in Tagoloan, Misamis Oriental and the fourth phase from Iligan City to Linamon town, Lanao del Norte. The project aims to cut the present 90-minute travel time by buys between Cagayan de Oro and Iligan to 15-20 minutes.
< Edited >
A feasibility study for the project is being reviewed and deliberated by the NEDA Regional Office 10, but a more detailed FS still need to be determined. Initial timetable points to a phased project implementation through PPP to be undertaken in 2011.
< Edited >
Phase 1 calls for the construction of a 124-km railway line from Iligan City to Cagayan de Oro City in Mindanao.
It will traverse ten coastal municipalities in Misamis Oriental, namely: Lugait, Manticao, Naawan, Initao, Libertad, Gitagum, Laguindingan, Alubijid , El Salvador and Opol.
Earlier, the project was scheduled to start in 2011 with the initial spur of the first phase between Cagayan de Oro City and the new airport in Laguindingan, Misamis Oriental.
But the entire project would take 5-7 years to complete.
====