Re: Subic-Clark Cargo Railway Project
« Reply #1 on: December 19, 2017, 05:46:49 PM »
Feasibility study for Subic-Clark Cargo Railway now up for NEDA board approval
Updated August 23, 2017, 12:09 PM
By Madelaine B. Miraflor

https://business.mb.com.ph/2017/08/22/feasibility-study-for-subic-clark-cargo-railway-now-up-for-neda-board-approval/

The feasibility study for the P57.2-billion Subic-Clark Cargo Railway project is now up for National Economic and Development Authority (NEDA) for approval, which, if obtained, could already pave the way for state-run Bases Conversion and Development Authority (BCDA) to start the project before the year ends.

Subic-Clark Cargo Railway Project is a 77-kilometer rail connection linking Subic Port with Clark International Airport mainly to reduce the number of trucks travelling in Metro Manila and lower the prices of goods.

The project also aims to increase Subic Port Utilization and compliment airport operation in Clark.

< Edited >

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11949
    • View Profile
    • The ADROTH Project
« Last Edit: October 29, 2019, 12:42:11 PM by adroth »

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11949
    • View Profile
    • The ADROTH Project
Re: Subic-Clark Cargo Railway Project
« Reply #3 on: October 10, 2018, 12:23:57 PM »
Subic-Clark railway construction begins 2019
June 3, 2018 | 8:09 pm   
The government’s plan to build a cargo train connecting Subic to Clark is targeted to start next year.

By Denise A. Valdez

https://www.bworldonline.com/subic-clark-railway-construction-begins-2019/

THE government’s plan to build a cargo train connecting Subic to Clark is targeted to start next year, Budget Secretary Benjamin E. Diokno said.

< Edited >

He said the P50.03-billion railway is part of the government’s 75 flagship infrastructure projects. It will be funded through an official development assistance from the Chinese government.

Although the train system is originally intended for cargo to maximize the use of the Subic port, Mr. Diokno said it may eventually be used for passenger travel.

The Subic-Clark cargo train has been approved by the National Economic and Development Authority Investment Coordination Committee (NEDA-ICC) in January. In April, NEDA said it is one of the projects up for review by the Board.

< Edited >

The Bases Conversion and Development Authority (BCDA) is in charge of the project. It also manages the Clark International Airport expansion, the New Clark City Mixed Use Industrial Real Estate developments, New Clark City-National Government administrative center, New Clark City-Food Processing Terminal and International Food Market and Broadband Backhaul Modular IT Facilities.

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11949
    • View Profile
    • The ADROTH Project
Re: Subic-Clark Cargo Railway Project
« Reply #4 on: October 10, 2018, 03:18:48 PM »
Preps begin for Phase 1 of PNR Clark railway project
By PTV News - January 6, 2018

http://defenseph.net/drp/index.php?action=post;topic=579.0;last_msg=12994

MARILAO, Bulacan — The Department of Transportation (DOTr) and the Philippine National Railways (PNR) began Friday various preparations for the construction of the first phase of the PNR Clark railway project that will run from Tutuban in Manila to Malolos in Bulacan province.

Pre-construction activities include site clearing, grading of unleveled surfaces, and demolition of obstructions to the PNR line.

Transportation Secretary Arthur Tugade said the department is committed to pursuing measures, such as doing parallel activities, to fast-track the completion of the railway project.

Tugade noted that based on previous practices, site clearing works had to wait after the awarding of a project to a general contractor.

“DOTr understands the need to complete this project faster. That is why we pursued these works parallel with the procurement of the general contractor, which is scheduled to be selected by the second quarter of 2018 for PNR Clark Phase 1,” Tugade said in his address during the commencement of works for the railway project in Barangay Tabing-Ilog in Marilao, Bulacan.

Tugade also appealed to Bulacan’s local government officials to assist the department in right-of-way issues by informing their constituents of the benefits of the railway system.

“Tulungan ninyo kami sa right of way. Hindi namin kakayanin mag-isa yan. Tulungan ninyo kami na masabihan ang ating mga kababayan na tatamaan ng proyekto para ito sa ikabubuti ng sambayanang Pilipino (We seek your help in settling right-of-way issues. We cannot do this alone. Help us inform those who might be affected by the construction of the railway project that this is for the benefit of our countrymen,” Tugade said.

< Edited >

Phase 1 of the PNR Clark Project involves the construction of the rail system along the 38-km. segment from Tutuban, Manila to Malolos, Bulacan. Once completed in 2021, it will have 10 stations and is expected to serve an estimated 340,000 passengers daily.

The National Economic and Development Authority (NEDA) has already approved Phase 2 of the project, a 70-km. stretch from Malolos, Bulacan to Clark, Pampanga, to be further extended north to La Union, Tuguegarao, and the Subic Freeport. (Aerol John Pateña/PNA)

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11949
    • View Profile
    • The ADROTH Project
Re: Subic-Clark Cargo Railway Project
« Reply #5 on: November 01, 2018, 02:33:01 AM »
Subic-Clark rail awaits contractor nominees from Beijing
ABS-CBN News
Posted at Oct 31 2018 12:24 PM

https://news.abs-cbn.com/business/10/31/18/subic-clark-rail-awaits-contractor-nominees-from-beijing

MANILA - The Philippines will defer the signing of the commercial agreement for the China-funded Subic-Clark Railway, pending a list of 3 potential contractors from Beijing, a Filipino official said Wednesday.

The agreement may be signed later this year or early 2019 and may not be done in time for Chinese President Xi Jinping's visit to Manila in November, said Transportation Undersecretary Timothy John Batan.

< Edited >

The Subic-Clark railway is on track for completion in 2021, he said.

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11949
    • View Profile
    • The ADROTH Project
Re: Subic-Clark Cargo Railway Project
« Reply #6 on: June 12, 2019, 12:57:20 PM »
Understanding President Duterte’s approval ratings
June 3, 2019 | 12:23 am
By Andrew J. Masigan

https://www.bworldonline.com/understanding-president-dutertes-approval-ratings/

< Edited >

The 71-kilometer Subic-Clark cargo railway has obtained NEDA approval and is in the advanced stage of preliminary works. The DOTr is hoping to commence construction next year.

< Edited >

adroth

  • Administrator
  • Boffin
  • *****
  • Posts: 11949
    • View Profile
    • The ADROTH Project
Re: Subic-Clark Cargo Railway Project
« Reply #7 on: July 16, 2019, 02:41:14 PM »
https://www.facebook.com/DOTrPH/videos/2398409617083638/

Today, the Department of Transportation (DOTr), through Secretary Arthur P. Tugade, will sign the contract for Package 3 of PNR Clark Phase 1 with J-Trec & SC JV, as represented by Corporate Officer and General Manager of Sumitomo Corporation's Social Infrastructure Business Division, Hiroshi Karashima.

Contract Package 3 of the 37.6-kilometer mass transit project pertains to the manufacture and delivery of rolling stock.

The contract signing will be witnessed by DOTr Usec. for Railways Timothy John Batan, Usec. for Legal Affairs Reinier Paul Yebra, Usec. for Finance Garry de Guzman, Asec. for Procurement Giovanni Lopez, Atty. Celeste Lauta as the representative of Philippine National Railways (PNR) General Manager Junn Magno, Japan Transport Engineering Company President Takao Nishiyama, and Sumitomo Corporation of the Philippines President Seiji Takano.

Contract Package 1, which was signed on 20 May 2019 and is now on full swing, covers the construction of six stations (Solis, Caloocan, Valenzuela, Meycauayan, Marilao, Bocaue) and a depot. Contract Package 2, signed on 23 January 2019 and is on full-blast construction as well, consists of the construction of three stations (Balagtas, Guiguinto, Malolos).

Once PNR Clark Phase 1 is completed and fully operable by 2022, travel time from Manila to Bulacan will be reduced from one (1) hour and 30 minutes to just 35 minutes. A rail segment of the North-South Commuter Railway (NSCR), PNR Clark Phase 1 is expected to serve 300,000 passengers daily.